Date: Tue, 23 Oct. 2000
From: Phil Pierce
To: Gabrielle Buel
Cc: Pat Kane, Joe Nelson
Subject: Re: Looking good
Hi Gabrielle - it is going well and starting to go faster. As of now, the truss work is done. The floor beams are in. The siding will probably be finished in a day or two. The long deck panels should be going in any time now. The north abutment is being finished on the approach with some short sections of stone retaining walls. The south approach is going to be left as is until the bridge will roll up to the abutments and be moved over the water. After the bridge is on the abutments, then the approach will be finished. Don't know if the metal roofing will go on before or after the move (if it wrinkles during the move [I don't think it will but won't guarantee it.], then it would have to be replaced.). They could be ready to move it in two weeks. We have a lot of details to work out about the move and it will be well rehearsed before we set a date.
Phil