October 31, 2020: The Bridgeport Covered Bridge restoration progress.

Herb Lindberg details the August bridge progress:

As in the September report, many aspects of the rehabilitation and restoration of the covered bridge across the South Yuba River at Bridgeport, CA are in process here:

  1. disassemble 2015 stabilization structure (towers, bridge support beams, cable system,
  2. remove rejected old floor beams and hang new replacement beams in place,
  3. create bolster beams by sistering pairs of timbers,
  4. construct concrete forms and rebar grids for north abutment front, back and wing walls,
  5. receive and inspect rust-resistant steel truss tie bars,
  6. drill holes into 2015 stabilization-cable deadman concrete and bond rebar extensions from north abutment pile cap into them,
  7. place and vibrate concrete into north abutment front, back and wing walls,
  8. place and vibrate concrete blocks around rebar from north abutment pile cap to 2015 stabilization cable deadman concrete,
  9. begin construction of upper bridge-chords, and the tie and cross beams from east to west chords,
  10. restore truss terminus buttress posts by installing dutchman patch blocks into removed decayed sections.

Click below to watch the YouTube video titled: October Bridge Progress..

For more information about the Bridgeport Covered Bridge got to: South Yuba River Park Association website.

Our thanks to Will Truax for passing this information along in The Covered Bridge Experience Facebook group.

HTML5 logo