Herb Lindberg details the August bridge progress:

As in the July reports, many aspects of the rehabilitation and restoration of the covered bridge across the South Yuba River at Bridgeport, CA are in process here:

  1. square the distorted end buttresses to ensure uniform transfer of truss loads to abutment reaction forces, and remove rot from the buttress timbers;
  2. continue return of truss braces into their lower and upper shoes;
  3. continue installation of pile cap rebar at both the north and south portals;
  4. create footings in the rebar for portal moment frames;
  5. place concrete into north portal rebar to complete its pile cap and moment frame footings,
  6. and install the north portal moment frame onto its footings.

Click below to watch the YouTube video titled: August Bridge Progress..

For more information about the Bridgeport Covered Bridge got to: South Yuba River Park Association website.

Our thanks to Will Truax for passing this information along in The Covered Bridge Experience Facebook group.

HTML5 logo